● DEMO MODE
Demo workspace · Changes stay in this browser. Sample schedule: October 6, 2026.
DUVTECH FIELD MANAGER
Job scorecard
Johnson — Deck Repair
Contract revenue$7,850
Actual revenue$3,925
Estimated cost$4,850
Actual cost$4,136
Gross profit · actual revenue-$211
Actual margin-5.4%
Where the money went
$714 favorable| Cost category | Estimated | Actual | Variance |
|---|---|---|---|
| labor | $2,400 | $2,160 | $240 |
| materials | $1,850 | $1,526 | $324 |
| equipment | $300 | $250 | $50 |
| subcontractors | $0 | $0 | $0 |
| Mileage / travel | $100 | $80 | $20 |
| other | $200 | $120 | $80 |
Cost-to-date variance is provisional; remaining work is not forecast.
Time & delivery
- Estimated labor hours
- 40 hrs
- Actual labor hours (demo rate $60/hr)
- 36.0 hrs
- Estimated duration
- 5 calendar days
- Actual duration
- Not recorded
- Target completion
- 2026-10-09
- Actual completion
- Not recorded