—JOB SCORE / 100Scoring model not defined
Contract revenue$7,850
Actual revenue$3,925
Estimated cost$4,850
Actual cost$4,136
Gross profit · actual revenue-$211
Actual margin-5.4%

Where the money went

$714 favorable
Cost categoryEstimatedActualVariance
labor$2,400$2,160$240
materials$1,850$1,526$324
equipment$300$250$50
subcontractors$0$0$0
Mileage / travel$100$80$20
other$200$120$80

Cost-to-date variance is provisional; remaining work is not forecast.

Time & delivery

Estimated labor hours
40 hrs
Actual labor hours (demo rate $60/hr)
36.0 hrs
Estimated duration
5 calendar days
Actual duration
Not recorded
Target completion
2026-10-09
Actual completion
Not recorded